Select and appoint the Commissioning Provider
After reading this guide, you will be able to procure and appoint an independent Commissioning Provider before design begins. You will know how to run a qualifications-based selection and lock in a contract that gives your CxP enforceable authority to direct testing and withhold sign-off.
Purpose of the step
This ‘how to’ is part of the ASHRAE Stage 1 series. It supports Step 1 of the Pre-Design commissioning process.
For the full Stage 1 overview, see the Stage 1 guideline.
The purpose of Step 1 is to appoint a qualified, independent Commissioning Provider at the start of the pre-design stage, before the project programme is set, the design brief is issued, and the design team is engaged. Standard 202-2024, Section 5.1.1 assigns CxP selection as an Owner responsibility at project initiation. Guideline 0-2019, Section 5.2.1 governs the CxP's appointment requirements, independence obligations, and authority over the commissioning process.
In practical terms, this step ensures that:
✅ The CxP is in place before any commissioning-shaping decisions are made.
✅ The selection is conducted through a structured two-stage process—an RFQ to shortlist on qualifications, followed by an RFP for proposals and fee—ensuring technical capability is evaluated before cost is considered [Guideline 0-2019 Informative Appendix E].
✅ The CxP's independence from the design and construction entities is validated and confirmed [Guideline 0-2019 Informative Appendix L Sections L2.2–L2.4].
✅ The Professional Services Agreement [PSA] gives the CxP authority to direct testing, require remediation, and withhold sign-off [Guideline 0-2019 Section 5.2.1]. Without that authority written into the contract, the CxP can observe and report. They cannot enforce.
✅ All pre-conditions for Step 2 are met; the CxP is contracted, in position, and ready to form the commissioning team.
Inputs and Outputs
Required Inputs
Expected Outputs
Step Checklist
- Shortlisting criteria record completed before the RFQ is issued: minimum individual qualifications and comparable project experience thresholds defined, formatted as a dated one- or two-page table, and retained in the Stage 1 procurement file.
- Two-stage selection process completed: RFQ shortlist established on qualifications alone; RFP issued to shortlisted firms; technical proposals and fee proposals evaluated separately.
- Shortlisted candidates interviewed, with the project team who will lead the Cx work present at the interview.
- Proposals scored against the recommended 100-point framework, with a documented record for each firm
- Reference checks completed using the multi-party contact lists submitted, including construction manager and facilities administrator contacts, not only Owner contacts.
- CxP holds recognized professional certification [e.g., CCP, BCxP, or equivalent under ISO/IEC 17024]
- CVs of named alternate personnel reviewed and confirmed adequate for project scale and programme.
- CxP confirmed independent from the designer of record and construction management firm; independence verified at organisational level, not only declared
- Where a conflict of interest exists [e.g., the CxP shares a parent company with the designer], it is formally documented, organizationally separated, and a management plan is in place before the PSA is signed.
- Signed separate Professional Services Agreement [PSA] in place with the Owner: scope, deliverables, schedule, and authority defined across all project stages.
- Authority clause confirmed as enforceable: CxP has express authority to direct testing, reject non-compliant results, and withhold commissioning sign-off until remediation is verified
- Named key individual written into the contract with a substitution clause specifying required notice period and Owner approval process.
- CxP appointed at the initiation of the project. Practically, this means the appointment is complete before the project programme is set, the design brief is issued, and the design team is engaged.
How to
Section 4 covers the full procurement and appointment sequence across seven sub-steps.
Work through them in order: timing and the conditions that must be in place before the RFQ goes out.
Quick reference:
4a: Establish when the appointment must happen
4b: Independence verification before the selection
4c: Structure and run the two-stage selection process
4d: Define and review the RFP submission requirements
4e: Compare fee proposals where divergence exists
4f: Execute the Professional Services Agreement [PSA]
4g: Confirm pre-conditions for Step 2
The most damaging version of Step 1 is one that happens too late. We consistently see CxPs appointed at Design Development, sometimes later, and asked to work backwards against a design that is already substantially fixed.
This happens because "project initiation" is often misunderstood as the start of design rather than the start of project planning, leaving the CxP to inherit a brief they had no part in setting.
To prevent this, the CxP appointment must be sequenced as the very first project activity, this will ensure that the CxP can actually govern the Pre-Design stage.
- Confirm that the CxP appointment is initiated before any of the following occur: the project programme is set; the design brief is issued; the design consultant is engaged.
- Begin informal market conversations early, as by the time a project is formally declared, the most capable commissioning firms may already be committed elsewhere.
- Confirm that the Owner's Representative or Project Manager has the authority, experience and mandate to run a formal selection process and execute a Professional Services Agreement. If delegated authority is unclear, resolve it now, before the RFQ is issued. If it is determined that there is not enough commissioning experience in the team to do the work then look to employ some support from an experienced company.
- Document this timing decision as the opening entry in the Step 1 record: date project initiation was declared, and confirmation that no design brief, designer engagement, or programme-setting activity will proceed until the CxP appointment is complete.
What to Watch
"Project Initiation" is treated as the date the design consultant submits their first drawing, not as the date the commissioning procurement process should already be underway. By that point, Step 1 has already failed.
Common Issues
Key Terms
Decision Points
This table highlights the key decisions required to establish a working control structure.
Timing and sequencing
Step 1 begins at the point the project is identified and the Owner decides to proceed. It continues until the Professional Services Agreement [PSA] is executed and the Commissioning Provider [CxP] is formally in position. The appointment must be complete at the initiation of the project. This means it must happen before any Pre-Design commissioning work begins, and therefore before any of the following occur: the project programme is set, the design brief is issued, or the design consultant is engaged.
- Earliest start: At initial project identification, before the procurement of any other consultants or the establishment of the master project programme.
- Latest acceptable start: Before the design brief is issued. Any later and the CxP inherits decisions they should have shaped.
- Dependencies: Step 1 has no commissioning predecessor; it opens at project identification. However, it is the absolute predecessor to every other Pre-Design step. Step 2 cannot begin until the PSA is signed and the CxP is formally appointed.
- Market awareness: Informal conversations with CxP firms can and should begin before Step 1 is formally opened; often 6 to 12 months ahead of formal procurement on complex projects; to confirm market capacity before the RFQ limits options.
- Execution hard stop: The PSA must be signed before the CxP attends any Pre-Design meeting or contributes to any Pre-Design document. The procurement decision is not the starting point; the executed contract is.
Roles and Responsibilities
RResponsible
Issues RFQ and RFP; manages evaluation panel and shortlisting process; coordinates contract negotiation; verifies authority clause and independence documentation; issues formal appointment letter; confirms authority clause language before Owner signs.
AAccountable
Appointment decision; independence determination; PSA execution.
CConsulted
IInformed
PSA executed [date confirmation].
Documents Produced
This table summarises the main records this step should generate, who owns them, what they contain, and where they are used later.
ASHRAE References
Assigns CxP selection and the determination of the commissioning scope as an Owner responsibility at the exact initiation of the Commissioning Process.
Defines the CxP as an objective advocate for the Owner [Section 4]. Governs the appointment of the CxP, assigns leadership responsibility, and mandates the documentation of lines of authority [5.2.1]. Defines the conflict of interest condition, and dictates the strict organizational separation and management plan required if a conflict is unavoidable [App L].
Provides the qualifications-based selection framework used throughout this step: minimum individual engineer criteria [E5]; submission requirements including multi-party references [E6]; the recommended 100-point scoring model [E7]; and two-stage selection process guidance including interviews [E8].
Defines the formal Pre-Design commissioning obligations for project parties. Used to assign the appointed CxP's leadership duties [21.2(a)], justify embedding strict co-operation clauses in the design services RFQ [21.1(a)], and confirm construction manager obligations where appointed early [21.4(a)].
Provides an example RFQ format, guidance on qualification criteria, proposal scope definition, and commissioning services scope.
Provides best practice guidance for initiating the commissioning process: Owner responsibilities, procurement approach, and early OPR foundations.