Form your commissioning team and issue the Cx Organization Chart
After reading this guide, you will be able to understand how to form an independent commissioning team, verify stakeholder decision authority, preserve the Commissioning Provider’s (CxP) independence, and issue an accepted Cx Organization Chart.
Purpose of the step
This 'how to' is part of the ASHRAE Stage 1 series. It supports [Phase 1, Step 2] of the Pre-Design commissioning process.
For the full Stage 1 overview, see the Stage 1 guideline.
The formal purpose of [Phase 1, Step 2] is to form the commissioning team, confirm decision authority for every member, and issue the Cx Organization Chart as the accepted governance record before any structured Pre-Design commissioning activity begins. This enacts [Guideline 0-2019 Section 5.2.1.1], which requires a CxP Team to be formed during Predesign to oversee, implement, and accomplish commissioning activities, with each member available for meetings, qualified to contribute to OPR development, and holding authority to make binding decisions for the organisations they represent.
In practical terms, this step ensures that:
- The CxP's reporting line to the Owner or Owner's Representative [see Key Terms] is formally documented and independent of the design and construction entities before any Pre-Design work proceeds.
- Every team member's decision authority is checked and recorded, so the first OPR workshop session is not derailed by the discovery that the people in the room cannot actually commit to anything.
- FM and O&M personnel are included at this step, giving their operational knowledge the opportunity to shape the OPR before design assumptions overwrite it.
- The project has a usable delivery structure, a record that answers "who decides this?" and "who needs to be in the room?" at every subsequent Pre-Design activity.
- The decision matrix governing meetings, issue escalation, and formal approvals at [Phase 1, Steps 3], [Phase 1, Step 7], [Phase 1, Step 8], [Phase 1, Step 10], and [Phase 1, Step 11] is built from agreed information.
Inputs and Outputs
Required Inputs
Expected Outputs
Step Checklist
- Owner / Owner's Representative is named, their commissioning acceptance authority confirmed in writing, and any delegation to the Project Manager [PM] is documented before the Cx Organization Chart is drafted.
- CxP is listed as team lead for the commissioning process, with a direct reporting line to the Owner or Owner's Representative confirmed and independent from design and construction entities.
- Project Manager [PM] is listed with their authority level stated explicitly: what they can decide in the room, what requires escalation to the Owner, and what is reserved for formal Owner acceptance.
- FM and O&M personnel are named as active team members, not deferred to construction or listed as future observers.
- End-user and occupant representatives are identified, with their scope of contribution confirmed relative to the OPR workshop agenda.
- Written authority confirmation received from every participating organisation before the first OPR-related session is scheduled.
- Cx Organization Chart drafted showing CxP reporting directly to Owner / Owner's Representative, independent of design and construction entities.
- Cx Organization Chart issued for review and all CxP Team comments resolved.
- Formal written Owner acceptance of the Cx Organization Chart obtained and recorded with date and version number.
- Delivery method reviewed and any adjustments to team composition or phasing documented, with CxP independence preserved regardless of procurement route.
- Accepted chart distributed and used to set [Phase 1, Step 3] meeting attendance lists, distribution, and governance basis.
How to
Section 4 covers the full team formation and governance mapping sequence across seven sub-steps. Work through them in order to ensure authority is documented before any structured Pre-Design commissioning activity begins.
Quick reference:
- 4a. Identify the core Pre-Design commissioning team
- 4b. Verify decision authority for every team member
- 4c. Draft the Cx Organization Chart
- 4d. Adjust team composition for project delivery method
- 4e. Obtain written authority confirmation from every participating organisation
- 4f. Issue the Cx Organization Chart for review and obtain Owner acceptance
- 4g. Use the accepted chart to oversee the next steps
Do not just list personnel. Every team member must have confirmed authority to make decisions and commit resources for their organization. Guideline 0-2019 sets the standard directly: team members must hold authority to make decisions binding on the organisations they represent.
The following steps build that list systematically, starting with the parties who carry the requirements the OPR must capture.
- List Owner-side participants first: Owner or Owner's Representative [decision authority and budget holder], Commissioning Provider [team lead, independent of design and construction], and Project Manager [PM] if a PM structure exists and is not a decision authority for commissioning.
- Add FM and Facilities Management personnel. [Guideline 0-2019 names FM as an essential Predesign participant and links FM inclusion directly to better OPR content, particularly on maintenance access, lifecycle requirements, and operational capability.
- Add O&M personnel. Their knowledge of how existing buildings in the Owner's portfolio actually perform is the one input that translates directly into verifiable OPR requirements that maintenance teams will be able to work against.
- Add end-user or occupant representatives where building function, occupancy patterns, security requirements, or mission-critical activities affect what the OPR must capture.
- Separately identify subject matter experts [SMEs] whose technical input the OPR will need [e.g., HVAC controls specialists, IT and cybersecurity representatives]. Guideline 1.1-2025 and Guideline 1.5-2012 provides discipline-specific checklists that help the CxP confirm which SME categories apply. Identify them now so the CxP can schedule their input before the OPR is drafted.
- Document each participant's organisation, role on the project, and whether they are an active participant at Pre-Design or a later joiner who simply needs to be identified now.
- Do not include design consultants or contractors in the core Pre-Design team at this step unless the delivery route has already brought them into the project. Guideline 0-2019 confirms that active membership changes by phase; later participants join as procurement or appointment milestones occur.
What to Watch
The Owner's procurement team includes a name on the list without checking whether that person can actually attend key sessions or make binding decisions. The individual is nominated on paper, the position is filled in the chart, and the gap does not surface until the OPR workshop, where the person in the room says they will need to take everything back for sign-off.
Confirm availability and authority together, not as separate conversations.
Common Issues
Key Terms
Cx Organization Chart
The formal diagram showing the commissioning team structure: who is on it, what role and authority each member holds, and how the CxP sits in the governance hierarchy for commissioning decisions and escalation. Distinct from the project's general org chart.
Escalation path
The documented route by which a decision that exceeds a team member's authority is passed upward to a party who can resolve it, within a defined timeframe.
FM Personnel
People responsible for managing the facility and coordinating the services, resources, and activities that help keep it functional, safe, comfortable, and efficient. In commissioning, they represent the facility-management perspective and help prepare the building for operation.
O&M Personnel
Staff who operate building systems and equipment and perform or coordinate their routine, preventive, and corrective maintenance. In commissioning, they provide operational input, participate in training and testing, and take responsibility for operating and maintaining systems after handover.
Decision Points
This table highlights the key decisions to establish a working control structure for this step.
Timing and sequencing
[Phase 1, Step 2] begins immediately after the CxP appointment is executed at [Phase 1, Step 1] and the Owner-side structure is clear enough to identify the participants. It continues until the Cx Organization Chart is formally accepted.
- Earliest start: When the CxP appointment is executed [Phase 1, Step 1] closes and Owner-side participants can be identified.
- Latest acceptable start: Immediately after [Phase 1, Step 1] closes.
- Dependencies: [Phase 1, Step 2] must close before [Phase 1, Step 3] (meeting and reporting protocols) begins, because meeting structures, attendance expectations, and escalation paths cannot be set without a confirmed team map.
- OPR milestone: [Phase 1, Step 2] must close before the OPR workshop is scheduled. The workshop requires confirmed attendance by all active Pre-Design team members with documented authority.
- FM/O&M integration: FM and O&M availability must be confirmed at this step. Their participation in [Phase 1, Step 7] (OPR workshop) is critical; confirming them late leaves no time to prepare their input.
- Later stage participants: Design consultants and contractors are not members of the core Pre-Design team at this step unless already engaged by the process. Their future inclusion should be shown as outline entries in the chart.
- Change control: Any change to the team, authority, or reporting lines after the chart is initially accepted requires a formal chart revision and Owner acceptance before the change takes effect.
Roles and Responsibilities
RResponsible
Confirms governance structure and delegation scope; nominates Owner-side participants; provides written authority confirmation; formally accepts the Cx Organization Chart.
AAccountable
Final acceptance authority for the Cx Organization Chart and for all Owner-side authority delegation decisions. Acceptance must be in writing with version number and date.
CConsulted
Consulted by CxP on team composition gaps, authority boundary decisions, escalation structure, and PM delegation scope.
IInformed
Informed of subsequent revisions and team membership changes requiring chart update.
Documents Produced
This table summarises the main records this step should generate, who owns them, what they contain, and where they are used later.
ASHRAE References
Mandates the formation of the CxP Team during Pre-Design. Dictates that team members must be available, hold binding decision authority for their organisations, and have their lines of authority formally documented
Identifies essential Pre-Design participants, specifically mandating the inclusion of FM and O&M personnel from the outset to ensure operational knowledge shapes the OPR
Confirms that the CxP Team evolves by project phase. Used here to distinguish between the core Pre-Design team that must be confirmed now, and future participants who simply join at later procurement milestones
Explicitly assigns the CxP the responsibility to "organize and lead the CxP Team" (item a), establishing the CxP as the party responsible for team governance.
Requires the Owner to include defined Cx roles and responsibilities in the Design and Construction Teams' contracts. Ensures team obligations are anchored in normative standards
Provides guidance on initiating the process, securing stakeholder buy-in, and ensuring Cx participation is written as a contractual requirement rather than left as a courtesy arrangement
Requires the Cx Plan to include individual responsibilities and communication protocols, establishing the direct link between Step 2's org chart outputs and the initial Cx Plan developed at Step 10.
Illustrates the communication structure showing the CxP reporting directly to the Owner (Figure 07-01), and explicitly advises that this separate relationship is necessary to avoid conflicts of interest and preserve independence.
Offers supplementary guidance on allocating team roles and integrating them into project contracts. Crucial for resolving authority boundaries on design-build or multi-party delivery routes
Explains team roles from a stakeholder perspective. Supports the Step 2 approach of confirming participation expectations for every party before the first OPR session begins