Update the Cx team and confirm roles for the Design Stage
Learn how to update your Commissioning (Cx) Team and confirm member roles before Design Stage commissioning begins. Aligned with ASHRAE Guideline 0-2019 and Standard 202-2024, this guide covers verifying binding decision authority, briefing replacement FM and O&M staff on the accepted OPR, integrating early ECI contractors, and reissuing the approved Cx Organisation Chart prior to the Stage 2 Kick-off Meeting.
Purpose of the step
This step establishes the structure, authority, and committed availability of the Commissioning (Cx) Team for Stage 2, ensuring all roles are verified before Design Stage commissioning commences. This process directly implements [ASHRAE Guideline 0-2019, Section 6.2.1], [ANSI/ASHRAE/IES Standard 202-2024, Section 5.2.1], and the roles and responsibilities framework set out in [SSPC 300 Annex 21].
This step guarantees that:
✅ The design team is formally integrated as active commissioning participants from the commencement of Stage 2, with named discipline leads holding the binding authority required to resolve review findings on behalf of their companies.
✅ Any changes to Facility Management (FM), Operations & Maintenance (O&M), Owner or any other CxP Team member representation since the Stage 1 OPR workshop are identified and updated, ensuring new personnel are fully briefed on the accepted OPR and initial Cx Plan before they participate in design reviews or Basis of Design (BOD) decisions.
✅ On Early Contractor Involvement (ECI), design-build, or two-stage tendering delivery, construction contractors engaged during the Design Stage are formally integrated into the Cx Team with their commissioning obligations clearly documented from the point of their engagement.
✅ You must identify and escalate any authority gaps, representation gaps, or team structure issues to the Owner in writing before the Stage 2 Design Kick-off Meeting [Stage 2, Step 3], ensuring all roles are fully resolved prior to the first design review cycle.
✅ The updated Cx Organisation Chart is in active circulation before the Design Stage Kick-off Meeting [Stage 2, Step 3], ensuring every participating party understands the team hierarchy and reporting lines before the session begins.
Inputs and Outputs
Required Inputs
Expected Outputs
Step Checklist
- Update the Cx Organisation Chart: Revise the chart to reflect the active Stage 2 team, including all named design team leads and key technical discipline leads as active commissioning participants.
- Verify Binding Decision Authority: Confirm and record that every named Cx Team member holds the formal, written authority to make binding commissioning decisions on behalf of their parent organisation.
- Resolve Representative Gaps: Document and report any designated team member who lacks binding decision authority to the Owner in writing, establishing a clear path to obtain a delegate with full signing power.
- Verify and Brief FM, O&M Personnel & Others: Confirm current Facility Management (FM), Operations & Maintenance (O&M) and other personnel assignments. For any new representatives who did not attend the Stage 1 OPR workshop, conduct a formal briefing session and obtain their written sign-off confirming they have read and understood the accepted OPR and initial Cx Plan.
- Confirm Design Lead Autonomy: Verify that the appointed design team commissioning lead holds direct, contracted authority to respond to and resolve CxP design review findings without being delayed by a secondary internal corporate approval loop.
- Integrate Early Construction Contractors: On projects utilizing Early Contractor Involvement (ECI), design-build, or fast-track procurement, formally add all engaged contractors to the Cx Team roster and document their specific design-phase commissioning obligations from the day they are appointed.
- Formally Escalate Resource Gaps: Submit any outstanding gaps in team authority, resource availability, or stakeholder representation to the Owner as a formal, written escalation record, and log the Owner's written direction.
- Distribute the Updated Chart: Issue the revised and version-controlled Cx Organisation Chart to all team members, securing written confirmation of receipt and archiving the distribution record in the central project document management system.
- Prepare for the Kick-off Meeting: Place the updated Cx Organisation Chart, the stakeholder briefing records, and all unresolved authority escalation records on the pre-distributed agenda for the Kick-off Design Commissioning Meeting [Step 3] to ensure immediate team verification.
How to
This section defines the chronological sequence of six sub-steps required to update, verify, and formally establish the Stage 2 Commissioning (Cx) Team before any active design commissioning work begins.
Quick Reference:
✅ 4a: Review the Stage 1 Cx Team record and identify what has changed
✅ 4b: Confirm binding authority for every Cx Team member
✅ 4c: Brief replacement FM and O&M participants
✅ 4d: Integrate ECI and Design-Build contractors (where engaged)
✅ 4e: Update and reissue the Cx Organisation Chart
✅ 4f: Escalate unresolved gaps to the Owner before the Kick-off Meeting
The Commissioning (Cx) Team established at Stage 1 was built around Pre-Design Phase participants: the Owner's representatives, the Commissioning Provider (CxP), and pre-design programming professionals. Even if the design professionals were appointed early enough to observe Stage 1, Stage 2 is when they officially transition into active commissioning members. Additionally, it is common for the Owner's FM or O&M representation to have changed since the OPR workshop. You must compare the Stage 1 Cx Team record against the current project directory, identify every change, and treat each shift as a gap requiring written resolution before Stage 2 proceeds.
- Review the accepted Cx Organisation Chart from [Stage 1, Step 2] and list every named member, their role, and their confirmed authority level.
- Contact the Owner's Representative to check current FM and O&M representation. Find out who attended the OPR workshop and who is assigned to [Stage 2] now.
- Confirm which design team leads are appointed and which engineering disciplines are active in [Stage 2].
- For ECI, design-build, or fast-track projects, check with the Owner's Representative to see which construction contractors are hired. Check if commissioning tasks are written into their contracts.
- Write down every change to the [Stage 1, Step 2] Cx Team list as a gap that needs a formal solution (such as new members to add, departed members to replace, or changed roles).
What to Watch
Compare the Stage 1 records side-by-side with the current project directory. Do not just do a quick scan, because a quick scan easily misses personnel changes. If an O&M representative has changed since the OPR workshop, you must formally brief the new person on the accepted OPR and Cx Plan before they start design reviews.
Common Issues
Key Terms
Cx Team
The full group of specialists and representatives who carry out the commissioning work. Led by the Commissioning Provider [CxP], this team includes Owner representatives, facility operators [FM and O&M], design leads, and early contractors.
Cx Organization Chart
The formal diagram showing the commissioning team structure: who is on it, what role and authority each member holds, and how the CxP sits in the governance hierarchy for commissioning decisions and escalation. Distinct from the project's general org chart.
Binding authority
The power to make decisions, issue instructions, or enter agreements that legally or contractually commit another party. Unlike an advisory role, it allows a person to act on that party’s behalf within the applicable limits of their authority.
Early Contractor Engagement (ECI)
A project method where construction contractors are hired early during the Design Stage [Stage 2] instead of waiting for the Construction Stage [Stage 3]. Their commissioning duties start as soon as they are hired.
Cx Team Record
The accepted team chart and list of members from the Pre-Design Stage. This is used as the starting point for the team review.
Authority gap
When a team member does not have the written power to make decisions for their company. This gap must be reported to the Owner in writing and resolved before the Kick-off Meeting.
Decision Points
This table highlights the key decisions to establish a working control structure for this step.
Timing and sequencing
Step 1 begins at the start of the Design Stage [Stage 2]. It runs at the same time as [Stage 2, Step 2](checking design contract obligations) [Step 2]. You must complete [Step 1] before the [Stage 2] Kick-off Meeting [Step 3] begins.
- Earliest Start: Start this step as soon as the Owner accepts the [Stage 1] Closeout Report and gives the official order to start [Stage 2].
- Latest Acceptable Start: You must complete the updated Cx Organisation Chart and collect all written authority forms before you issue the Kick-off Meeting [Stage 2, Step 3] agenda. Send these documents to the team at least 48 hours before the meeting.
- Dependencies: [Step 1] runs at the same time as [Stage 2, Step 2]. You cannot start the Kick-off Meeting [Stage 2, Step 3] until [Step 1] is fully complete.
- Handling Early Design Work [Fast-Track Projects]: On some projects, design work starts early or informally before [Stage 2] officially begins. If this happens, you must complete [Step 1] immediately. Do not wait for the next project milestone. You must confirm team roles and authority before the team conducts any design reviews.
- Contractor Additions: On ECI or design-build projects, you must add construction contractors to the Cx Team within five working days of their official appointment.
Roles and Responsibilities
RResponsible
Assigns FM and O&M representatives for [Stage 2]; confirms OR authority level for [Stage 2] decisions; responds to written escalations from CxP on authority gaps
AAccountable
Formal authority to accept or reject the organisation chart for the [Stage 2] Cx Team; accountable for all unresolved gaps proceeding into [Stage 2] with Owner acceptance
CConsulted
IInformed
Receives updated Cx Organisation Chart; receives written record of all authority gap escalations and their resolution
Documents Produced
This table summarises the main records this step should generate, who owns them, what they contain, and where they are used later.
ASHRAE References
Establishes that CxP Team members must be available for meetings, have qualifications to contribute to the work, and hold authority to make decisions binding on the firms and constituencies they represent; the authority confirmation requirement in 4b derives directly from this clause.
Establishes that the CxP Team evolves as a project progresses and that contractors and vendors may join after they are under contract; on ECI routes, this means contractor Cx Team membership begins at engagement, not at Stage 3 contract execution.
Identifies the essential members of the Design Phase commissioning team, including the Owner's representatives, CxP, and design professionals
Defines the Design Phase Cx responsibilities of the CxP Team; the requirement to build and maintain cohesion and cooperation and to confirm RFP team roles are the direct basis for this step.
Mandates updating and expanding the commissioning plan during the Design Phase to add roles, responsibilities, and detailed milestones for construction
Requires that Construction Phase and Occupancy and Operations Phase roles and responsibilities of CxP Team members, including new members, be clearly defined based on unique experience and knowledge; professional and services agreements must be modified to reflect scope; this informs the ECI contractor documentation requirements at 4d.
Requires the Owner to formally accept the Basis of Design (BoD) and the updated OPR during the Design Phase, following the CxP's review
States that the Owner shall provide direction, reviews, and acceptance as required throughout the project and the Cx; the Owner's role in resolving authority gaps [Section 4f] and accepting the updated Cx Organisation Chart flows from this clause.
Requires the Owner to include in Design and Construction Teams' contracts their defined roles and responsibilities in the Cx; this underpins the escalation requirement at 4f where contractor or design team appointment gaps are found.
Obliges the Design Team, by contract, to review, respond to, and participate in resolving issues identified during the commissioning design reviews
Requires the Owner to approve the master Commissioning Plan and establish a process for approving any subsequent revisions
Requires the Design Team and Owner to respond to design review comments, and mandates that unresolved issues be escalated to the Owner for final direction
Provides detailed role descriptions and responsibilities for the Owner [21.1], Cx Provider [21.2], and Design Professional [21.3] in a comprehensive Cx; used as the authority and responsibility framework underpinning the RACI table in Section 9 and the authority confirmation requirements in 4b.
Requires the Owner to assign operations and maintenance (O&M) personnel to participate in Design Phase coordination meetings
Mandates that the CxP prepare the initial Commissioning Plan and update it during each phase of the project
Requires the Design Professional to attend design coordination meetings and respond to CxP review comments in a timely manner
Establishes that the Design Team is responsible for preparing its portion of O&M documentation and specifying requirements for contractors
Outlines the Planning and Design Phase expectations, stipulating that the scope of O&M documentation must be established during design
Outlines the matrix of responsibilities for developing, updating, and approving O&M and Systems Manuals during the design phase