Conduct the final Stage 4 Commissioning Review [Final Milestone]

This guide details Step 23 of the ASHRAE Stage 4 occupancy and operations commissioning process. Learn how to conduct a rigorous, document-based final commissioning review to verify all deliverables, test records, training obligations, and contractor callbacks before seeking Owner sign-off. The guide outlines methods to audit and disposition the Issues and Resolution Log, confirm Systems Manual and Basis of Design (BOD) currency, assemble a structured CxP Recommendation Memorandum, and lead an informed Owner review session to ensure a seamless closeout under ASHRAE Guideline 0 and Standard 202.